Blister machine proposal comparison
Compare both proposals against one approved product, pack, accepted-output target, inspection boundary, documentation list and FAT protocol. The machine name alone cannot establish an equivalent project.
A defensible comparison
A useful DPP-260 vs IMA blister-machine comparison begins only after both suppliers receive the same user requirement specification. Public model names, catalogue speeds and country of origin do not prove that the quoted lines will produce the same accepted pack.
Dosage form, geometry, fragility, orientation, dust, batch profile and representative samples.
Cavity drawing, forming web, lidding, seal system, artwork, perforation and cut criteria.
Feeding, forming, sealing, inspection, rejection, coding, changeover and line interfaces.
URS response, approved trials, document index, FAT protocol, raw data and deviation closure.
| Decision area | Buyer input required | DPP-260 response to confirm | Other proposal response to confirm |
|---|---|---|---|
| Forming route | Approved barrier requirement, web grades, thicknesses and cavity drawing. | Quoted forming configuration, tooling, usable web window and trial boundary. | Quoted forming configuration, tooling, usable web window and trial boundary. |
| Accepted output | Good packs per shift, run time, changeovers, reject rules and planned stops. | Packs per cycle, verified run condition, yield basis and stated exclusions. | Packs per cycle, verified run condition, yield basis and stated exclusions. |
| Feeding | Actual product samples, orientation, dust, fragility and mixed-product risks. | Feeder concept, manual touchpoints, challenge conditions and reject handling. | Feeder concept, manual touchpoints, challenge conditions and reject handling. |
| Inspection & data | Defect list, detection limits, code checks, user roles, records and interfaces. | Included hardware/software, test method, data boundary and unavailable functions. | Included hardware/software, test method, data boundary and unavailable functions. |
| Changeover | Format family, cleaning boundary, target time and approved measurement method. | Parts changed, tools required, staffing, settings, samples and FAT demonstration. | Parts changed, tools required, staffing, settings, samples and FAT demonstration. |
| Documents & services | Language, format, approval, execution, site support and handover responsibilities. | Named deliverables, exclusions, revisions, execution owner and commercial status. | Named deliverables, exclusions, revisions, execution owner and commercial status. |
Swipe horizontally to review all comparison columns.
Project-fit gate
The DPP-260 should be evaluated as a configured blister process, not as a universal substitute for another model. These five gates determine whether a like-for-like proposal can be prepared and tested.
Accepted-output comparison
Two proposals are not comparable if one quotes a mechanical maximum and the other quotes accepted finished packs. Calculate the target from the actual pack layout and production schedule, then place the same acceptance method in both requests.
Evidence before equivalence
A supplier name, component brand or compliance statement does not by itself establish process suitability, data integrity or finished-pack acceptance. The evidence package must be named before the purchase order.
Approved protocol, prerequisites, challenge products, material lots, sampling plan, calibrated instruments and acceptance limits.
Configuration baseline, settings, start/stop times, total output, accepted output, defects, rejects, waste and deviations.
Approved report, deviation disposition, drawings, manuals, certificates in scope, backups, spare-parts list and open-item register.
Lifecycle cost without invented numbers
Do not compare a headline machine price with a different project boundary. Request itemized commercial responses, enter the same planning horizon and record every assumption that materially changes the result.
Prepare a comparable request
HIJ can respond to a DPP-260 project request against the buyer’s stated scope. If you already have another proposal, remove commercially sensitive fields you do not wish to share and provide the technical requirements, included-scope list and open questions that must be normalized.
Continue the buying decision
Buyer questions
IMA and related model names are trademarks of their respective owner. HIJ Machinery is not affiliated with or endorsed by IMA. This page provides a buyer-side comparison framework and does not claim that differently configured machines are interchangeable.
Move from model names to testable scope
Send the approved inputs you already have. Open items can be recorded as assumptions or trial requirements instead of being hidden behind a generic comparison.