Agree what is delivered
A useful factory acceptance test connects named products, material lots and pack formats to a defined run. Agree the duration, sampling method, accepted-output target and reject criteria before the trial.
- Product and pack record
- Identify samples, material references, drawing revisions and the configuration used. Keep the format schedule with the trial record.
- Machine-function checks
- Include normal running, missing-product challenges, reject handling, sealing and cutting behaviour, stop/restart and the specified changeovers. Record good output, rejects, stops and settings.
- Finished-pack evidence
- Define the required test methods, sampling and acceptance criteria. Assign which checks occur during the machine trial and which need separate laboratory work, and who reviews the results.
- Document deliverables
- Itemise drawings, operating and maintenance instructions, parts lists, material records, calibration information and any agreed qualification support. A general “GMP documentation” label is not a complete deliverables list.
One scope, clear responsibilities
Separate equipment supply from site procedures, product approval and regulatory responsibilities. Name the supplier, customer or appointed specialist responsible for each open item in the proposal.